|
By Melissa Beecher
Thursday, November 28, 2002
WAYLAND - A
federal judge has ordered the Zoning Board of Appeals to authorize
construction the town's first cell phone tower, ending an 8-year legal
dispute.
Under
the order issued by U.S. District Court Judge Robert Keeton, the town
will now be require to let Nextel put a cell phone antenna on an
existing 97-foot Nstar transmission tower along Rte. 20.
For
nearly 10 years, Nextel has contended that service gaps exist in
Wayland and a tower was needed near the town center to provide better
service for customers.
The
legal case arose out of the ZBA's February denial of Nextel's request
for a height variance to install the antenna on the tower, which is
outside the town's wireless communications district.
In his
ruling, Keeton says the ZBA decision was "not supported by substantial
evidence" and was in violation of the federal Telecommunications Act
of 1996.
"Obviously, I am pleased and Nextel is pleased with this decision,"
said Steven Grill, the attorney representing Nextel. "The is the
culmination of a long effort to provide service to that part of the
state. I think that decision speaks for itself."
Town
officials expressed frustration at the decision, and said that an
appeal has not yet been ruled out.
"We are
disappointed that Judge Keeton chose to side with Nextel in this case,
but we believe we proffered an aggressive defense on behalf of the
town and the Zoning Board of Appeals," said Selectman Brian O'Herlihy.
"I think that an appeal is still under consideration, although I don't
think that there is a lot to appeal in this situation.
"The
board felt, and continues to feel, it was important to defend the
town's wireless communications bylaw," said O'Herlihy. "While the
outcome of this case is not what we hoped for, we were able to develop
some useful technical information during the preparation of the town's
defense that the board believes will provide us with a sound technical
basis for enforcing the wireless district bylaw in the future."
No money
damages were sought by Nextel, and the town will only need to pay for
its own legal costs. This case was the first test of the town's
wireless communications bylaw since its enactment in May 1999.
Nextel
has sought to place an extension on the Nstar tower that would rise 11
feet 8 inches, bringing the total height to 108 feet 8 inches. The
height exceeds the town's 35-foot height maximum that exists in the
historic zoning district.
In the
decision, Keeton said, "Circumstances existing in this case
demonstrate that any further efforts of Nextel are likely to be as
fruitless as its efforts up to this point. The alternative sites, even
if technically feasible in the abstract, do not overcome the
undisputed evidence in the record of the town's hostility to the
provision of wireless service."
"Nextel
had met its heavy burden of showing the town's hostility, and
therefore that any further efforts would be so likely to be fruitless,
that it is futile even to try," the judge stated.
In 1995,
Nextel filed a plan with the Planning Board. The board granted a ANR
(approval not required), freezing zoning bylaws for the applicant's
proposal. Since that time, a new wireless zoning district was
established, which Nextel claimed did not effectively allow it to
provide services.
An
official order of the U.S. District Court in Boston is expected to be
issued sometime prior to the end of the year.
|